Electric Power Generation Applications with the State Corporation Commission


Case Number Applicant Proposed Facility Location Status
PUE-2002-00305 White Oak Power Co. 680MW, gas-fired Dry Fork, Pittsylvania County Filed 6/02
PUE-2002-00150 James City Energy Park, LLC 580MW, gas-fired James City County Filed 4/02
PUE020075 CPV Warren, LLC 530MW, gas-fired Warren County Filed 2/02
PUE020003 Old Dominion Electric Cooperative 696MW, gas-fired Remington, Fauquier County Filed 12/01
PUE010722 Kinder Morgan Virginia, LLC 560MW, gas-fired Cumberland County Filed 12/01
PUE010721 Duke Energy Wythe, Inc. 620MW, gas-fired Jacksons Ferry, Wythe County Filed 12/01
PUE010659 Chickahominy Power, LLC 665MW, gas-fired Charles City County Filed 1/02
PUE010657 Buchanan Generation, LLC 88MW, gas-fired Buchanan County Approved 6/02
PUE010477 CPV Cunningham Creek, LLC 520MW, gas-fired Fluvanna County Approved 10/02
PUE010430 Mirant Danville, LLC 870MW, gas-fired Danville Filed 8/01; interim approval 4/02
PUE010429 Tenaska Virginia II Partners, LP 900MW, gas-fired Buckingham County Filed 8/02
PUE010423 Kinder Morgan Virginia, LLC 560MW, gas-fired Brunswick County Filed 7/01
PUE010303 Old Dominion Electric Cooperative 463MW, gas-fired Louisa County, near Gordonsville Approved 7/02
PUE010169 CinCap-Martinsville, LLC 330MW, gas-fired Martinsville Filed 3/01
PUE000343 Virginia Power 540MW, gas-fired Possum Point power generating stations, Prince William County Approved 3/01
PUE000092 Doswell Limited Partnership 171MW, gas-fired Hanover County Approved 6/00
PUE000009 Virginia Power 320MW, gas-fired Ladysmith, Caroline County Approved 10/00
PUE990785 Wolf Hills Energy, LLC 250MW, gas-fired Bristol Approved 5/00